Building on Lesson Learned for Expanding the Next Phase of the
Groundwater Replenishment System
William Dunivin
1
*, Mehul Patel, P.E
1
. and James H. Clark, P.E.
2
1
Orange County Water District
2
Black & Veatch
*
Corresponding author e-mail: BDunivin@ocwd.com
ABSTRACT
This paper discusses operational information on one of the world’s largest indirect potable reuse
projects, the Groundwater Replenishment (GWRS). This project includes a large treatment
facility known as the Advanced Water Purification Facility (AWPF) and went into service in
January 2008. During the first two and a half years of operations numerous issues were
identified with the initial plant design. These issues served as “lessons learnedand were able to
be addressed in the first planned expansion of the existing facility. The solutions to these issues
are discussed in detail and can serve as guidance to other utilities considering implementation of
a large scale reclamation facility.
KEYWORDS:
Advanced Water Purification Facility, Microfiltration, Reverse Osmosis, Ultraviolet Light, Flow
Equalization, Lime Post Treatment, Decarbonation
INTRODUCTION
GWRS is a water supply project constructed by the Orange County Water District (OCWD) and
Orange County Sanitation District (OCSD). The GWRS supplements existing water supplies by
providing a reliable, high-quality source of water to recharge the Orange County Groundwater
Basin (Basin) and to protect the Basin from further degradation due to seawater intrusion. By
recycling water, the GWR System also provides peak wastewater flow disposal relief and
indefinitely postpones the need for OCSD to construct a new ocean outfall by diverting treated
wastewater flows that would otherwise be discharged to the Pacific Ocean.
Project Overview
GWRS was put into operation in January 2008. Located in central Orange County, the project
extends from Huntington Beach, Fountain Valley, and Costa Mesa near the coast to Santa Ana,
Orange, and Anaheim generally along the Santa Ana River. The GWR System consists of three
major components: (1) AWPF and pumping stations; (2) a major pipeline connecting the
treatment facilities to existing recharge basins; and (3) expansion of an existing seawater
intrusion barrier. The locations of the main project components are shown on Figure 1.
Figure 1. GWRS map.
Advanced Water Purification Facility
The major AWPF processes include microfiltration (MF), reverse osmosis (RO), advanced
oxidation process (AOP), which consist of ultraviolet (UV) light and hydrogen peroxide. A
process flow diagram of the AWPF is provided in Figure 2. The maximum production capacity
of the original AWPF is approximately 265 megaliters per day (MLD or 70 million gallons per
day [mgd]) and will be expanded to 379 MLD (100 mgd) for this Initial Expansion Project.
Figure 2. AWPF Process Flow Diagram.
OCSD clarified secondary effluent, normally disposed to the ocean, first goes through a
screening process prior to MF membrane treatment. MF is a low-pressure membrane process
that removes suspended matter from water. MF specifically is used to separate suspended and
colloidal solids including bacteria and protozoa from the OCSD secondary effluent. Sodium
hypochlorite is added to the MF feedwater to minimize MF membrane fouling. MF filtrate is fed
to RO, and MF reject streams are returned to OCSD’s Plant No. 1 for treatment. MF has
demonstrated exceptional effectiveness as a pretreatment for RO. Based on a design recovery of
approximately 89 percent, 326 MLD (86 mgd) of filtrate is produced by MF. Excess filtrate is
sometimes used to supplement tertiary non-potable reuse.
Prior to RO treatment, the MF filtrate passes through polypropylene wound cartridge filters. The
RO process rejects most dissolved contaminants and minerals. Particularly, RO treatment
reduces dissolved organics, pesticides, total dissolved solids, pharmaceuticals, silica, and viruses
from MF filtrate. Generally, constituents with a molecular weight above 100 are removed by
RO. Sulfuric acid is added to the RO feedwater for pH reduction and carbonate scaling control.
A threshold inhibitor or antiscalant is also added to minimize membrane fouling. The RO
permeate is then directed to UV treatment. The RO concentrate or brine is discharged into the
ocean via the existing OCSD ocean outfall. Based on a design recovery of approximately 85
percent, the production rate of RO is 265 MLD (70 mgd).
Following RO, the RO permeate undergoes UV treatment. UV treatment involves the use of UV
light to penetrate cell walls of microorganisms, preventing replication and inducing cell death.
UV thus provides additional bacterial and viral inactivation and, combined with RO treatment,
increases removal efficiency. With the addition of hydrogen peroxide, UV light and the
hydroxyl radicals oxidize organic compounds for ultimate removal from water. UV and
peroxide treatment are used for N-Nitrosodimethylamine (NDMA) and other low molecular
weight organics removal. UV product water then undergoes additional chemical treatment prior
to groundwater injection and recharge. After RO treatment, the product water is so low in
mineral content that it has a corrosive nature. This can be mitigated with the addition of lime
and decarbonation. If this did not take place, the concrete lined transmission pipe would corrode
in the presence of the unstabilized water.
The success of the GWRS has allowed for the planning and design of the first expansion from
265 MLD (70 mgd) to 379 MLD (100 mgd). OCWD plans to purify additional flows made
available by OCSD's new Steve Anderson Lift Station (SALS). Although the SALS facility
originally was planned for nighttime operation to make up for flow depressions, OCSD now
intends 24 hour a day operation to increase the overall supply of treated wastewater. Knowing
the GWR System treatment facility can operate at various flows, the expansion can include
greater capacity to accommodate the higher flows available during the day. In addition, OCSD
is currently under construction to expand its secondary treatment processes, which is expected to
be completed in late 2011 to provide an increased flow of secondary treated water to AWPF.
This 114 MLD (30 mgd) expansion could result in a minimum average increase of
approximately 60 MLD (16 mgd or 18,000 acre-feet per year [afy]) of production from the GWR
System. Expansion of the GWR system is a viable option based on the current success of the
GWR System and the availability of other recharge sources for OCWD that would bring the total
production of up to 304 MLD (80 mgd or 90,000 afy). In addition, flow equalization of
secondary effluent is being evaluated to maximize the production of the GWR System to the full
379 MLD (100 mgd or 112,000 afy).
The OCWD Water Production Staff has been operating the GWRS since January 2008. The
experience gained during the first two years of operations was used to help improve the existing
treatment process and for the design of the expansion. OCWD staff has worked closely with
Black & Veatch, the expansion’s design engineer, throughout the design process. The lessons
learned during the first two years of operation have been instrumental in the expansion design.
Additional MF, RO, and UV light treatment equipment will be purchased and installed. The
design also includes flow equalization, improvements to the lime stabilization process, additional
pumps, and electrical gear. A significant portion of the infrastructure was constructed as part of
the original design to accommodate this expansion. This includes the yard piping, pump
stations, and the electrical backbone.
Equipment procurement was a unique component of the original design involving the MF and
UV equipment. As a result of the original competitive process, Siemens and Trojan supplied the
equipment for the MF and UV, respectively, based on lowest life cycle present worth cost. Pre-
selection documents, for MF equipment and UV equipment, were incorporated into the design
drawings allowing for these specific equipment manufacturers at an established price. The
equipment purchase was then assigned to the construction contractor. The same approach is
being used for the expansion.
While the treatment train remains the same, the expansion includes numerous challenges
associated with the design. In addition, construction sequencing to reduce downtime of an
existing operational facility is a huge factor to consider. Other design challenges include
updating the process control system (SCADA), improving the lime postreatment system for
varying flows, and accommodating for an ultimate build out of 493 MLD (130 mgd).
RESULTS
Using Lesson Learned for the Design of the GWRS Initial Expansion
OCWD began operating the 265 MLD (70 mgd) GWRS in January 2008. At the time, OCSD
had not completed the construction of the SALS to bring more water into its treatment plant
during the daily low flow period. There was enough treated secondary effluent during the hours
of 9 am to 10 pm to operate the AWPF at the design flow of 265 MLD (70 mgd). However,
night time flows dropped to as low as 95 MLD (25 mgd) between the hours of 10 pm and 9 am.
The intent of the original design was to always operate the AWPF at a steady flow, but doing so
would have capped production at the lowest diurnal flow of 95 MLD (25 mgd). After staff
gained experience operating the AWPF, efforts began to operate the plant in response to diurnal
flow variations and to treat as much water as possible. There were many challenges with the
process control programming, including the operations’ staff learning how to operate the various
processes. This included taking the MF, RO, and UV systems in and out of service at the right
time to maintain process recovery and efficiency. One of the biggest challenges was learning to
control the RO product water decarbonation and lime stabilization process.
In an effort to proceed with the design of the GWRS Initial Expansion, OCWD staff met
internally with engineering and operations and maintenance staff to discuss what was learned
during the original design and construction and operation of the AWPF. The review included the
design engineer selection process as well as what staff learned during the first two years of
operations. A list was also developed of issues or improvements desired for the existing facility.
These improvements were to be incorporated into the design of the 114 MLD (30 mgd) initial
expansion.
One of the first steps was the selection of the design. The original design of the GWRS was a
large effort which included the design of a $300 million treatment plant, 8 injection wells, and a
22.6 kilometers (14 mile) transmission pipeline. Due to the magnitude of the design, various
design firms were contracted under the lead designer at the request of the owner. This was
requested to prevent the lead designer from being overburdened with every aspect of the design.
One of the lessons learned was that it was appropriate to have various firms design the GWRS as
long as different firms were not working in the same disciplines. With differing preferences,
approach to detail development, and general design approach, design firms were producing
conflicting designs within the same areas. It was learned that the best approach was to make sure
one firm handled the civil design; one firm handled electrical design, and so on. With the design
of the expansion, the level of effort is much smaller yet it was important to maintain consistency
across the various disciplines.
When the GWRS was designed and constructed, all piping, facilities, electrical systems, and the
site were designed for an ultimate capacity of 493 MLD (130 mgd). Because the major
processes (MF, RO, and UV light) are modular systems, adding additional equipment to increase
treatment capacity should be relatively simple.
Equipment Pre-selection
Specific to the MF and UV equipment, a pre-selection approach is being employed, as was done
for the original design. Based on demonstration testing performed at OCWD prior to the original
design, OCWD staff and the design engineer developed technical specifications to determine
which manufacturer was used. As a result of this competitive process, Siemens and Trojan
supplied the equipment for the MF and UV, respectively, based on lowest life cycle present
worth cost. Pre-selection documents, for MF equipment and UV equipment, were incorporated
into the design drawings allowing for these specific equipment manufacturers at an established
price. The equipment purchase was then assigned to the construction contractor.
For the initial expansion of the GWRS, it was important to match existing MF and UV
equipment due to the existing system equipment configuration, ease of stocking spare parts, and
meeting regulatory compliance issues. Because consistency in the plant expansion design is
preferred, OCWD entered into pre-selection agreements with the same manufacturers or
suppliers. While the purchase of the equipment is assigned to the contractor at the time of
construction, OCWD entered into agreements with both suppliers for equipment design. The
contracts are between OCWD and the MF or UV equipment supplier. This contract enabled the
treatment plant expansion design team to prepare the work required to design the facilities
necessary for the MF and UV systems.
Maximize RO Energy Efficiency
Energy recovery devices (ERD) was incorporated into the design of the new RO skids for the
initial expansion. Each new RO skid will have its own dedicated ERD to reduce overall energy
consumption of the RO system. In addition, the ERD will be integrated with a booster pump to
boost feed pressures to the 2
nd
and 3
rd
stage RO membranes, allowing for flux balancing between
RO stages and operational flexibility to prolong membrane life. Preliminary estimates indicate
that the ERD will save approximately 29 kilowatt (kW) per RO skid and have a payback period
of approximately five years (approximately $23,000 energy cost savings per year for each RO
skid).
Process Control System
The existing Process Control System (PCS) is an Emerson Process Management DeltaV
Distributed Control System (DCS). All the major process equipment, including MF, RO, and
UV, use the Emerson DeltaV process controllers and Emerson DeltaV operator workstations.
The existing PCS architecture includes a dual (100 Mbs) Ethernet process control network that
connects two operator pro-plus workstations, multiple operator stations distributed throughout
the plant, and process controllers also distributed throughout the plant. Redundant process
controllers are provided for critical areas. The operator pro-plus workstations are used for
software development and the operator workstations are used for the human machine interface
(HMI) graphic displays for monitoring and controlling the process.
The process control network communication medium is multi-mode fiber optic cable that is
installed in a star-topology. Each process area building connects to the Ethernet network in the
MF Server Room. Dual fiber optic cables are provided for the dual Ethernet process control
network. In addition to the process control network, two field device networks are provided:
Foundation FieldBus and DeviceNET. The Foundation FieldBus communication network is used
to connect the analog devices, such as transmitters and analyzers, and valves to the process
controllers, in lieu of the traditional hard-wire 4-20 milliamp (mA) signals. The DeviceNET
communication network is used to connect to discrete signals from equipment such as VFDs,
MCCs, power monitors, etc. The existing PCS architecture will be expanded for the upgrades
associated with the Initial Expansion Project. Foundation FieldBus and DeviceNET will be used.
Flow Equalization
Knowing the GWRS treatment plant can operate at various flows, the expansion of the GWR
System includes greater capacity to accommodate the higher flows available during the day. The
current Preliminary Design Report evaluated an expansion that would result in approximately an
additional 114 MLD (30 mgd) of production out of the GWRS. A concept to equalize secondary
effluent flow has been completed, which would help increase daily production to the full 379
MLD (100 mgd) production capacity by storing wastewater during the day when it is available
and feeding the plant at night during low flow periods. The existing OCSD treatment plant site
is heavily developed with limited opportunities for construction of new process facilities. There
are advantages to development of primary effluent equalization. However, after further analysis
and review of the plant site, it was concluded that primary equalization was not feasible. This
conclusion was primarily based on the absence of developable space for primary equalization
facilities.
The existing production capacity of the AWPF is 265 MLD (70 mgd), which requires an influent
flow of 379 MLD (100 mgd). Flows in excess of 379 MLD (100 mgd) are available from OCSD
during a portion of each day and are currently discharged to the Ocean Outfall via OCSD’s Plant
No. 2. Due to normal diurnal variations, raw wastewater flows arriving at Plant No. 1 fluctuate
between 243 and 644 MLD (64 and 170 mgd) throughout the day, resulting in periods of
shortfall and periods of surplus. Table 1 presents a summary of the inflows to Plant No. 1 as well
as losses (plant water pump station and Green Acres Project [GAP]). The resulting secondary
treated wastewater available to the AWPF is displayed in the table below. The production from
AWPF must be ramped up and down to align with the flow available from Plant No. 1. As a
result, the AWPF is unable to consistently achieve its full design production capability. This
situation will worsen as the Expansion Project becomes operational and requires an influent
supply of between 493 and 508 MLD (130 and 134 mgd) to make production of 379 MLD (100
mgd). The expanded AWPF will only be able to treat to its design production capacity during the
daytime hours when flows through Plant No. 1 are greater than 493 MLD (130 mgd). The diurnal
flow calculations show that a storage volume of 57,000 cubic meters (15 million gallons [MG])
is required to equalize flows through the day to provide a constant 493 MLD (130 mgd) to the
AWPF.
Table 1. Typical day total flow available to the GWR System.
Hour
(MLD)
(+)
(mgd)
(+)
(MLD)
(+)
(mgd)
(+)
(MLD) (+) (mgd) (+) (MLD) (-) (mgd) (-) (MLD) (mgd)
0:00
321 84.81 199 52.50 49 13.04 33 8.76 537 141.58
1:00
270 71.30 199 52.50 49 13.04 33 8.76 485 128.08
2:00
216 57.01 194 51.11 49 13.04 33 8.76 426 112.40
3:00
172 45.32 169 44.70 49 13.04 33 8.76 357 94.30
4:00
142 37.42 141 37.21 49 13.04 33 8.76 299 78.90
5:00
127 33.39 114 30.14 49 13.04 33 8.76 257 67.81
6:00
125 32.88 91 24.14 49 13.04 33 8.76 232 61.30
7:00
155 40.98 74 19.54 49 13.04 33 8.76 246 64.79
8:00
236 62.32 67 17.56 49 13.04 33 8.76 319 84.15
9:00
334 88.01 75 19.83 49 13.04 33 8.76 425 112.11
10:00
389 102.54 103 27.10 49 13.04 33 8.76 508 133.91
11:00
407 107.45 140 37.04 49 13.04 33 8.76 564 148.76
12:00
402 106.02 167 44.02 49 13.04 33 8.76 585 154.32
13:00
401 105.69 184 48.47 49 13.04 33 8.76 600 158.43
14:00
395 104.17 195 51.47 49 13.04 33 8.76 606 159.91
15:00
385 101.55 199 52.50 49 13.04 33 8.76 600 158.33
16:00
373 98.53 199 52.50 49 13.04 33 8.76 589 155.31
17:00
367 96.93 199 52.50 49 13.04 33 8.76 583 153.70
18:00
369 97.39 199 52.50 49 13.04 33 8.76 584 154.16
19:00
376 99.31 196 51.83 49 13.04 33 8.76 589 155.42
20:00
386 101.89 195 51.49 49 13.04 33 8.76 597 157.62
21:00
404 106.69 199 52.47 49 13.04 33 8.76 619 163.44
22:00
415 109.63 199 52.50 49 13.04 33 8.76 631 166.40
23:00
404 106.50 199 52.50 49 13.04 33 8.76 619 163.27
Average 315 83.24 162 42.84 49 13.04 33 8.76 494 130.35
Plant Water/GAP
Total
OCSD Plant No. 1
MF Backwash Waste
OCSD Plant No.
1
SALS
MF Backwash
Waste
Plant Water/GAP
Total
Hour
(MLD)
(+)
(mgd)
(+)
(MLD)
(+)
(mgd)
(+)
(MLD)
(+)
(mgd)
(+)
(MLD)
(-)
(mgd)
(-)
(MLD)
(mgd)
0:00
321
84.81
199
52.50
49
13.04
33
8.76
537
141.58
1:00
270
71.30
199
52.50
49
13.04
33
8.76
485
128.08
2:00
216
57.01
194
51.11
49
13.04
33
8.76
426
112.40
3:00
172
45.32
169
44.70
49
13.04
33
8.76
357
94.30
4:00
142
37.42
141
37.21
49
13.04
33
8.76
299
78.90
5:00
127
33.39
114
30.14
49
13.04
33
8.76
257
67.81
6:00
125
32.88
91
24.14
49
13.04
33
8.76
232
61.30
7:00
155
40.98
74
19.54
49
13.04
33
8.76
246
64.79
8:00
236
62.32
67
17.56
49
13.04
33
8.76
319
84.15
9:00
334
88.01
75
19.83
49
13.04
33
8.76
425
112.11
10:00
389
102.54
103
27.10
49
13.04
33
8.76
508
133.91
11:00
407
107.45
140
37.04
49
13.04
33
8.76
564
148.76
12:00
402
106.02
167
44.02
49
13.04
33
8.76
585
154.32
13:00
401
105.69
184
48.47
49
13.04
33
8.76
600
158.43
14:00
395
104.17
195
51.47
49
13.04
33
8.76
606
159.91
15:00
385
101.55
199
52.50
49
13.04
33
8.76
600
158.33
16:00
373
98.53
199
52.50
49
13.04
33
8.76
589
155.31
17:00
367
96.93
199
52.50
49
13.04
33
8.76
583
153.70
18:00
369
97.39
199
52.50
49
13.04
33
8.76
584
154.16
19:00
376
99.31
196
51.83
49
13.04
33
8.76
589
155.42
20:00
386
101.89
195
51.49
49
13.04
33
8.76
597
157.62
21:00
404
106.69
199
52.47
49
13.04
33
8.76
619
163.44
22:00
415
109.63
199
52.50
49
13.04
33
8.76
631
166.40
23:00
404
106.50
199
52.50
49
13.04
33
8.76
619
163.27
Average
315
83.24
162
42.84
49
13.04
33
8.76
494
130.35
Backwash waste flows from the MF system and reject from the RO membranes are returned to
the OCSD plant. MF backwash flow is recycled to the head of the west side primary
sedimentation basins for subsequent treatment. The RO reject is not recycled; it is returned under
residual pressure to the downstream side of primary effluent distribution box (PEDB) 2, from
where it is conveyed to Plant No. 2 for discharge through the Ocean Outfall. As part of the
Expansion Project, the capacity of the MF system would be increased, resulting in an increase in
the MF backwash flow returned to Plant No. 1 for treatment. The backwash flow is
approximately 10 percent of the throughput, so would increase the backwash flow from 38 MLD
(10 mgd) to approximately 49 MLD (13 mgd). OCSD has confirmed that Plant No. 1 requires a
plant water flow of up to 211 MLD ( 4,000 gallons per minute [gpm or 5.76 mgd) for its
operations. In addition, the GAP plant operated by OCWD requires a flow of 11 MLD (3 mgd).
These flows represent internal system losses and need to be subtracted from the available inflow
to Plant No.1.
Decarbonation and Lime Stabilization
The GWRS post-treatment facilities stabilize RO permeate using decarbonation and lime
addition. Challenges were experienced during the first year of operation in achieving the pH and
alkalinity targets and led to tailored, multi-approach changes developed during the Initial
Expansion Project to increase dose accuracy and reduce overall pH variability. The RO
permeate pH and the post-treatment target adjustments as shown in Table 2.
Table 2. Post treatment water quality adjustment.
Parameter
RO Permeate
Finished Product
Water
pH
5.0 to 6.0
7.8 to 8.0
Alkalinity, milligrams per liter (mg/L) as
calcium carbonate (CaCO
3
)
10 to 12
40 to 55
Calcium, mg/L
<0.1
3 to 4
Hardness
(1)
, mg/L as CaCO
3
<0.3
7 to 10
(1)
Calculated value.
OCWD uses decarbonation for initial increase of the pH by removal of carbon dioxide. A
portion of the RO permeate is bypassed so that some carbon dioxide levels are maintained for
conversion into bicarbonate alkalinity. Following decarbonation, lime addition further increases
the pH of the water and adds calcium (hardness) and alkalinity by converting the remaining
carbon dioxide to bicarbonate. In addition to corrosivity, the objective of the post-treatment
facilities is to eliminate the potential for scale formation (precipitation of calcium carbonate) and
plugging of the screens at the groundwater injection wells. The existing lime system consists of
large silos containing powder hydrated lime (calcium hydroxide), slurry mixing system, slurry
pumps, polymer system, and lime saturators (clarifiers). Hydrated lime is mixed with RO
permeate water to form a slurry with a solids content of 7 to 10 percent. This slurry is then
pumped using peristaltic pumps to a saturator used to settle the excess lime solids. In addition,
polymer is added to the saturator to aid in settling. The supernatant or product from the saturator
is then conveyed to the product water after UV treatment. The product from the saturator
contains 0.12 percent solids. The total dosage of lime varies from 15 to 22 mg/L.
The current lime slurry make up system does not offer fine control on the strength of slurry
produced. This has resulted in an inconsistent lime slurry strength, which makes it very difficult
to control the dosage of lime actually produced from the lime saturators. The powder lime
delivery system consists of a screw auger, which turns a set number of revolutions based on the
desired target volume of lime to be added. However, the auger becomes caked with solidified
lime over time resulting in an inconsistent volume of powder hydrated lime being added to the
lime slurry mixing tank. The inconsistency in the lime slurry strength coupled with the variation
in plant production flows has led to several episodes of over and under dosing of lime. The over
dosing of lime has led to an increase in final plant product water turbidity and downstream
injection well clogging.
As part of the Initial Expansion of the GWRS, improvements were identified to enhance post-
treatment performance and reliability, as follows:
Target a lower pH (7.8-8.0) and higher alkalinity (40-50 mg/L) in the final product water
to increase buffering capacity and to decrease variability in the water quality while still
meeting targets to avoid scaling.
Install flow meters and flow control valves at the decarbonation towers to achieve
reliable flow distribution to the decarbonation towers, and allow automated adjustment of
by-pass based on feed pH.
Increase the by-pass capacity around the decarbonation towers to support a higher
alkalinity target by maintaining higher levels of carbon dioxide for conversion to
bicarbonate alkalinity with lime addition.
Modify the existing decarbonation tower effluent configuration to provide individual lime
feed for decarbonated water and by-pass water with the objective of improved pH feed
back control for lime feed and thus a more accurate lime dose for improved process
control.
Replace lime slurry make-up system based on findings from a pilot testing program
which support replacement with the RDP Lime Slaking system to increase delivery
accuracy to the lime saturators.
Install an additional lime saturator to support higher plant flow rates and higher lime
dosages without increasing turbidity.
The shaded areas on Figure 3 identify the areas on the GWR System that would accommodate
the 30 mgd expansion.
Figure 3. Site layout for GWRS Initial Expansion.
DISCUSSION
The major work of the Initial Expansion is summarized in Table 3.
Table 3. Summary of major improvements in Initial Expansion.
Facility
Expansion Project
Facility
Expansion Project
Flow
Equalization
Installation of two above grade metal tanks. Each tank would hold 28,500
cubic meters (7.5 million gallons) and are 66 m (216 ft) in diameter and 11
m (35 ft) high. The tanks will be equipped with mixers or aerators to keep
wastewater from going stagnant while stored. The tanks are covered for
odor control and are filled by local pumps and emptied by gravity.
Provisions for sodium hypochlorite addition will be provided to control
biological growth.
Screening
Facilities
Incorporation of one additional (fifth) mechanical screen at the existing
concrete wetwell and installation of a plastics capture device.
MF
Installation of one complete new MF train (Train C) on the east side of the
system, addition of new MF equipment to the existing train on the west side
of the system (Basin E03 and E04), and addition of new modules to the
“spacer elements” installed for the original AWPF on both the east and west
side. A new blower in the MF east blower room with a new vacuum system
for Train C will be installed along with a second caustic tank installed at
A235. A total of 36 cells will make up the future MF facility. Installation
of a MF backwash pipeline to feed downstream of primary sedimentation
basins.
Transfer Pump
Station
Addition of one RO Transfer Pump and one MF Backwash Supply Pump.
Cartridge Filter
Addition of four new cartridge filters.
Chemical Feed
Additional of one sodium hypochlorite tank and one new hose pump. The
two existing 17 cubic meters (4,500 gallon) threshold inhibitor (TI) tanks
will be removed and replaced with 24.6 cubic meters (6,500 gallon) tanks.
One new TI metering pump will be added. The TI pump common discharge
piping header will be upsized to 2 inch diameter. The sulfuric acid pump
suction lines will be upsized to remove current pipe size reduction at pump
suction. Existing PVDF suction piping will all be replaced with alloy 20
piping. Pump discharge header will be upsized.
RO
Addition of 2 new membrane trains (6 units total). Each train will be
equipped with an RO Feed Pump controlled by a variable frequency drive
(VFD, and each unit will have an energy recovery device that can be taken
out of service if needed. The 6 new units will be 7 vessels high. The units
will have interstage flow meters and conductivity analyzers. The 6 new
units would be tied into the existing RO Clean-In-Place (CIP) systems. A
cartridge filter will be added to each existing CIP systems as well as tank
mixers.
UV
Addition of 2 new UV trains and expansion of 3 existing trains.
Decarbonation
Addition of one new decarbonation tower over RO Flush Tank A01 with
flow balancing and control capabilities provided for the existing and new
decarbonation towers. The decarbonation bypass capacity will be increased
by adding bypass piping to decarb tank at locations for future decarb
towers.
Lime System
Installation of new parallel Finished Product Water (FPW) channel. One
channel receives fully decarbonated water from tank A01 and the other will
Facility
Expansion Project
receive a mix of decarbonated and bypass water from tank A02. The new
parallel channel will have its own mixer and analyzer station (EC, pH,
turbidity). Each of the 5 existing ZMI skids will be replaced by a Tekkem
system. Four silos will be used (A02 will sit empty.) The Tekkem system
will consist of four, 1.5 cubic meter (400 gallon) slakers and two, 7.6 cubic
meter (2,000 gallon) slurry aging tanks located in the existing lime building.
A third saturator will be added in the road between decarbonation and lime
areas. The third saturator will be configured to run normally and provisions
provided for future use as a secondary settling tank receiving saturator
effluent from the other two existing saturators. There will be three separate
pinch valve lime slurry dosing assemblies (one per saturator). A 2 m (7 ft)
lime screw conveyor will be housed on each of the four silos to get powder
lime to slakers. New upsized bin activators will be installed on the four
silos.
Product /Barrier
Pump Station
One additional Product Water pump to supplement the existing seven
vertical pumps, which supply water to the Spreading Basins and the Barrier.
CONCLUSION
The GWRS has completed over two years of successful operations. The success of the first two
years established a basis for adding additional production to maximize recycled water out of the
GWRS. With the GWRS ultimate capacity of 493 MLD (130 mgd), this 114 MLD (30 mgd)
expansion will take advantage of a new OCSD lift station and increased treatment capacity from
their secondary treatment facility. The new 114 MLD (30 mgd) expansion will result in
approximately 60 MLD (16 mgd or 18,000 afy) of production from the GWR System. With flow
equalization, the average increase in production amount from the initial expansion will reach 102
MLD (27 mgd or 30,000 afy) allowing the GWR System to be operated near 379 MLD (100
mgd) consistently. The Initial Expansion of the GWRS is a cost effective project that develops a
high quality cost effective alternative to imported water in the Southern California region.
REFERENCES
Steve Foellmi, Jennifer Enson, Tim Phelan, Rich Terrazas (2009) Preliminary Design Report for the
Initial Expansion of the Groundwater Replenishment System; Irvine, CA.