hydroxyl radicals oxidize organic compounds for ultimate removal from water. UV and
peroxide treatment are used for N-Nitrosodimethylamine (NDMA) and other low molecular
weight organics removal. UV product water then undergoes additional chemical treatment prior
to groundwater injection and recharge. After RO treatment, the product water is so low in
mineral content that it has a corrosive nature. This can be mitigated with the addition of lime
and decarbonation. If this did not take place, the concrete lined transmission pipe would corrode
in the presence of the unstabilized water.
The success of the GWRS has allowed for the planning and design of the first expansion from
265 MLD (70 mgd) to 379 MLD (100 mgd). OCWD plans to purify additional flows made
available by OCSD's new Steve Anderson Lift Station (SALS). Although the SALS facility
originally was planned for nighttime operation to make up for flow depressions, OCSD now
intends 24 hour a day operation to increase the overall supply of treated wastewater. Knowing
the GWR System treatment facility can operate at various flows, the expansion can include
greater capacity to accommodate the higher flows available during the day. In addition, OCSD
is currently under construction to expand its secondary treatment processes, which is expected to
be completed in late 2011 to provide an increased flow of secondary treated water to AWPF.
This 114 MLD (30 mgd) expansion could result in a minimum average increase of
approximately 60 MLD (16 mgd or 18,000 acre-feet per year [afy]) of production from the GWR
System. Expansion of the GWR system is a viable option based on the current success of the
GWR System and the availability of other recharge sources for OCWD that would bring the total
production of up to 304 MLD (80 mgd or 90,000 afy). In addition, flow equalization of
secondary effluent is being evaluated to maximize the production of the GWR System to the full
379 MLD (100 mgd or 112,000 afy).
The OCWD Water Production Staff has been operating the GWRS since January 2008. The
experience gained during the first two years of operations was used to help improve the existing
treatment process and for the design of the expansion. OCWD staff has worked closely with
Black & Veatch, the expansion’s design engineer, throughout the design process. The lessons
learned during the first two years of operation have been instrumental in the expansion design.
Additional MF, RO, and UV light treatment equipment will be purchased and installed. The
design also includes flow equalization, improvements to the lime stabilization process, additional
pumps, and electrical gear. A significant portion of the infrastructure was constructed as part of
the original design to accommodate this expansion. This includes the yard piping, pump
stations, and the electrical backbone.
Equipment procurement was a unique component of the original design involving the MF and
UV equipment. As a result of the original competitive process, Siemens and Trojan supplied the
equipment for the MF and UV, respectively, based on lowest life cycle present worth cost. Pre-
selection documents, for MF equipment and UV equipment, were incorporated into the design
drawings allowing for these specific equipment manufacturers at an established price. The
equipment purchase was then assigned to the construction contractor. The same approach is
being used for the expansion.
While the treatment train remains the same, the expansion includes numerous challenges
associated with the design. In addition, construction sequencing to reduce downtime of an
existing operational facility is a huge factor to consider. Other design challenges include